Millstream WA16 9QG compliance installation
Mr Farrell, Millstream WA16 requested site visit to upgrade foul waste system to comply with Environment Agency binding rules, drainage survey completed by third party, unfortunately missed several drainage run ❌❌❌. Site visual / dye trace clarified drainage runs, quotation submitted / accepted, start 29th January 2024.
Drains segregated, sewage treatment plant repositioned within lawn area. Cheshire East building regulations, electric certification completed.
New 20 meter surface water drain direct to watercourse installed, work completed , site reinstated 12th February 2024. ( patio slabs, turf etc ). Ground work completed by Leon, weather conditions terrible 🌧️🌧️💦💦