Compliance upgrade in Lower Peover .WA16 9AX
Starting a compliance installation at Lower Peover today, Thursday 31st October 2024 following delivery to site by Marsh Industries, Enco PE10 sewage package treatment plant
Lads had excavation ready to place tank into position , concrete delivered at 1200 hours, building inspector on site at 1400 hours, all OK
Electrician booked to attend 1000 hours 1st November 2024, hopefully can reinstate area by Monday evening, final building inspection booked for 1400 hours on 4th November 2024, then we are ready to move to Burland Nr Nantwich, hope weather stays good 👍👍