We attended site at the White House in Flintshire to determine if the current septic tank adhered to the current Natural Resources Wales bind rules.
the property is served by a conventional septic tank, which outfalls into the adjacent farm land.
the tank is of the correct size for the property and has a NRW permit as is required
the issue with the outlet drainage is that the ground is saturated, water table higher than drainage field - hence area water logged
options available to install a sewage treatment plant, which could go to a water course if available, the daily discharge volume would be 0.9 m3 / day.
ACTIONS
we have contacted NRW to obtain confirmation if the treatment plant can discharge into the local stream, will the unit require nutrient neutrality treatment ( nitrogen / phosphate treatment ), hopefully we should be able to progress the inquiry within 7 - 10 working days