Pumping station installation

We have had a request regarding a down stairs toilet / wash room which was connected to a surface water drain, unfortunately due to levels we could not divert the foul drain to the existing sewage package treatment plant. Following discussions with our pumping station manufacturer we submitted a quote to install pumping station, uplift foul waste stream into existing drains to sewage treatment plant.

The quotation was accepted, work commenced Monday 16th October 2023, electric connection / certification ✔️,Cheshire East building control to sign off on 23rd October 2023

Problem solved - client happy - system complies with Environment Agency binding rules