Compliance installation - Yew Tree Farm Congleton

Starting work at Yew Tree Farm Congleton, weather had been terrible , snow melting, rain - and we had a Marsh Ensign PE06IPS sewage treatment plant to install.

As week progressed weather improved, all underground drainage pipework installed, tank location excavated, concrete base, strap eyelets installed, tank positioned in place, strapped, surround to turrets with C25 semi dry concrete, imported reclaimed / recycled sand to reinstate to ground level, clay spoil removed off site. All drainage connections made , electric connected, Cheshire East building control certificated, site left clean and tide, unfortunately we went over 2 days, but as normal lads worked week-end ensuring we finished by 20th January 2025 as requested by client 👌