We attended the Gables [ Preston area ],to confirm if the 4 bedroom properties septic tank complied with EA binding rules, a Home owners drainage survey was completed Wednesday 5th March 2025. Unfortunately the tank discharged into a stream located at the rear property boundary, no surface water entered the system

Marsh tank delivered 17th March direct to site, excavation completed / tank in position 18th, building control on site, passed, electric part ‘ p ‘ provided, all ground work reinstatement will be completed 21st March 2025, pm.

Paul’s team completed install on schedule, ready to start next job on 24th March - 👍👍👍