BRITTLES - PUMPING STATION to UNITED UTILITIES COMPLETED

We installed a twin foul pumping station designed / sized by Marsh Industries at Wistaston Sports Centre in September 2022, the unit was then ‘ moth balled ‘ while the management committee raised funds to make the connection to the United Utilities public sewer.

The connection to the public sewer was undertaken by Duttons Contractors, the work schedule will be completed 28th February 2023, at which time we will re attend site and divert flow from septic tank to pumping station In accordance with our quotation.

Diversion of foul waste from septic tank to pumping station will commence w/c Monday 6th February 2023..

Outstanding work to be completed, foul drainage pipework diversion, commissioning of pumping station and ground reinstatement.